We're making more room for you!

​

On Monday 14th of June 2021, we finally broke ground on our long awaited building project!  We're so excited to have you part of the journey.

​

We'll be using this page for regular updates, showing you the building plans and for funding progress.

​

Together we are making space for our community, there will be plenty of opportunity to contribute your ideas time and money to advance our project. 

​

If you do have any questions or ideas, please feel free to contact us.

DONATE
ITEMS

product-6009210132420-p-01_edited.png

Choose how you want to contribute by donating an item of furniture or building materials.

HELP US RAISE MONEY

GOAL:  Phase 1
R600 000

BANKING DETAILS

Account Name Grace Covenant Church

Account No 62398505043

Account Type Business Account

Bank FNB

Branch Centurion

Branch Code 261550

​

Please add reference = Building

1.png

Check out our gallery below for building updates

21 September 2021
21 September 2021
21 September 2021
21 September 2021
21 September 2021
21 September 2021
21 September 2021
5 August 2021

Bricks being delivered.

PHOTO-2021-07-26-12-43-17 3
PHOTO-2021-07-26-12-44-29 2
PHOTO-2021-07-26-12-48-15 2
PHOTO-2021-07-26-12-48-20

Raft foundations.

20 July 2021

Mom's Room & Toilet Demo

20 July 2021

Mom's room & toilet demo

20 July 2021

Men's Toilet Demo

16 July 2021

Men's Toilet Demo

16 July 2021

Ladies bathroom Demo

16 July 2021

Ladies bathroom Demo

8 July 2021

Bathroom foundations

8 July 2021
8 July 2021

Tiles in auditorium being removed.

8 July 2021

Raft foundations being laid for bathroom block

8 July 2021

Cafe door and window bricked up and plastered.

8 July 2021

Bathroom foundations being prepped.

8 July 2021

Windowsill outside Cafe being removed to make space for bench seating.

14 June 2021
14 June 2021

Removing paving

14 June 2021
14 June 2021
11 June 2021

Ready to start

10 June 2021

Removing Portico

10 June 2021

Removing Portico

10 June 2021

Removing Portico

8 June 2021

Preparing the courtyard for building.

8 June 2021

Preparing the courtyard for building.

8 June 2021

Preparing the courtyard for building.

8 June 2021

Preparing the courtyard for building.

8 June 2021

Removing fountain

8 June 2021

Before - Courtyard

14 June 2021

Before - Cafe Outside

14 June 2021

Before - Mother's Room

14 June 2021

Before - Mother's Room

14 June 2021

Before - Mother's Room

14 June 2021

Before - Men's Toilet

14 June 2021

Before - Ladies Toilet

14 June 2021

Before - Ladies Toilet

14 June 2021

Before - Auditorium

14 June 2021

Before - Auditorium

14 June 2021

Before - Auditorium

14 June 2021

Before - Auditorium

14 June 2021

Before - Cafe

15 June 2021

Before - Cafe

15 June 2021

Before - Cafe

15 June 2021

Before - Cafe